Auburn Lakes Custom Swimming Pool Construction Schedule - Spring, TX
DAY 1 - November 25th
Excavation began today on a custom built gunite swimming pool in Auburn Lakes, Spring, TX. The pool will have a 7' round spa raised 18", with a 4 function spa side switch. It will include a tanning ledge with two fountains and a moss rock waterfall with five weepers. Spring Pools will also be installing an Outdoor Kitchen complete with gas bar-b-que, sink, and refrigerator. The deck area around the spa will be raised six inches and have a gas fire pit.
Alden Bridge Custom Swimming Pool Construction Project - The Woodlands, TX
DAY 1 - July 13th Excavation
Started construction on an unique custom pool design. The pool was designed to incorporate an existing wood deck. Given the utility easement and the desire to have the spa positioned off the deck and a large entry for their daughter, the spa is going to be built within the pool entry. The first step will wrap around the spa, the second step will also be a large bench next to the spa.
DAY 2 - July 14th Steel & Stub Plumbing
DAY 3 - July 15th Gunite
DAY 4 - July 16 Plumbing
What a hot day. Temperature hovering near 100 degrees. The Spillers have been very kind in offering everbody plenty to drink. The Plumber and his crew were able to brave the heat and install all the plumbing, equipment and run the gas line in just over a day. Thanks everybody.
DAY 5 - July 17 Electrical
The electrical system for the pool was installed. Trenches were inspected, then backfilled.
DAY 6 & 7 - July 18 & 19 Weekend (No Work Scheduled)
Gunite being watered.....To keep from Cracking!
DAY 8 - July 20 (Rain Delay)
DAY 9 - July 21 Tile, Coping & Rock
Rock work along with tile and coping is started today. Depending on the size and complexity, the work can take several days. The Spillers chose to have flagstone waterline tile and flagstone coping. The pool also has a mini waterfall and seven weepers. The weeping rock is set into the beam of the pool wall to a point below the waterline. This design gives the pool a barrier from the yard, keeping unwanted debris out of the pool. This design also allows the pool to be placed next to the utililiy easements, allowing for a larger pool in a smaller backyard. The deck area is maximized between the house and the swimming pool.
DAY 10 - July 22 Tile, Coping & Rock
Fininshed setting the moss rock for the Waterfall and Weeping Rock. Also, the Tile and Coping was fininshed being installed. What a beautiful water feature on a free form pool. The flagstone tile and coping accents the moss rock very well.
DAY 11 - July 23rd Deck
The deck for the pool is started. The deck is laid out. The drains are installed. The steel is set into place.
DAY 12 - July 24 Deck
The pea gravel deck is poured, floated, and finished. We added an umbrella sleeve in the deck so the Spillers could shade themselves by the pool. The deck was poured level to the existing wood deck for an easy transition.
DAY 13 - July 25 Pebble Sheen
The pool is prepped for Pebble Sheen. The Spillers decided on Blue Granite Pebble Sheen. Pebble Sheen has a smaller aggregate than Pebble Tec, but the application process is the same.
DAY 14 - July 26 Sunday (No Work Scheduled)
DAY 15 - July 27 Pebble Sheen
The Pebble is installed in the pool. It has a milky coating that will be acided washed.
DAY 16 - July 28 Pebble Sheen
The Pebble Sheen is acid washed. The pool return fittings are installed. The pool is then filled with water.
Three Weeks Later....Another Custom Built Inground Gunite Swimming Pool Construction Project Completed by the Contractors at Spring Pools.
Custom Swimming Pool Construction Schedule - The Woodlands, TX
DAY 1 - June 10th
Broke ground on a freeform custom inground gunite pool in The Woodlands, TX. The pool design includes a beach entry top with flagstone and a three and a half ton moss rock waterfall with weepers. The swimming pool also will have a custom kidney shaped spa, raised 18", with seven spa jets. The rest of the details to follow.....
DAY 2 - June 11th
Finish installing the steel and stub plumbing by noon. Modern Method Gunite started and finished by late afternoon.
DAY 3 - June 12th
The customer has an energy efficient Pentair varible speed pump installed for the pool and spa. This allows for lower flow rate for filtrating the pool, while also allowing for a higher flow rate when operating the spa. This along with a Pentair cartridge filter and 400,000 btu heater is standard equipment with Spring Pools. The plumber starts on day 3 with temperatures reaching near 100 degrees. Progress is slowed, but will still be completed in two days.
DAY 4 - June 13th
Plumbing finished.
DAY 5 - June 14th
Sunday - No Work Scheduled
DAY 6 - June 15th
Electrical work is completed. Trenches are inspected and passed by Nesbit Inspections.
DAY 7 - June 16th
Trenches are backfilled. Tile and Coping work is started. The coping around the pool is Oklahoma flagstone. The customer chose a 1" ceramic mosiac tile for the waterline of the pool.
DAY 8 - June 17th
Tile and Coping continues. Moss rock waterfall is started.
DAY 9 - June 18th
The Tile, Coping and Rock work is finished. The customer requested some slight modifications to the amount of rock vs tile and coping to the pool. There was more tile and coping and less rock when it was all said and done. The beach entry will have an sleeve in the flagstone for an umbrella.
DAY 10 - June 19th
Made some changes to the deck layout. Enlarged the Pergola area, and curved the steps more. No other work scheduled.
DAY 11, 12 & 13 - June 20th, 21st, & 22nd
No Work Scheduled
DAY 14 - June 23rd
Finished forming up deck and installing drains. There will be four steps from the covered patio area down to the main deck. The steps will be trimmed in flagstone. The deck will be of pea gravel and have flagstone inlays.
DAY 15 - June 24th
No Work Schedule - Concrete Scheduled for Tomorrow
DAY 16 - June 25th
Last minute changes to deck. Customer decided to have Spring Pools build the retaining wall for the landscaping beds between the house and pool. Poured concrete and floated deck. Pea gravel deck, with flagstone inlays.
DAY 17 - June 26th
The Teels are having Pebble Tec installed as the lining for their pool. Spring Pools contracts with Modern Method to install Pebble Tec and Pebble Sheen. Today the pool is being prepped for Caribbean Blue Pebble Tec.
DAY 18 - June 27th
Pebble Tec is applied. It needs to harden before it can be acid washed.
DAY 19 - June 28th
Sunday. No worked scheduled.
DAY 20 - June 29th
Acid washed the Pebble Tec. Began filling the pool.
DAY 21 - June 30th
Finished filling the swimming pool with water. Pool Start Up Begins..... Time to Set Up Pool School!!!
30 Days Later.... Another Custom Built Inground Gunite Swimming Pool Construction Project Completed by the Contractors at Spring Pools.
Morgan Custom Swimming Pool Construction Schedule - The Woodlands, TX
DAY 1 - April 24th
Broke ground on a smaller custom pool in The Woodlands, TX. The pool design includes a mutli-level raised beam with three sheer decents. It has a 7' round spa, raised 6", with seven spa jets. The rest of the details to follow.....
Fleming Custom Swimming Pool Construction Schedule - Spring, TX
DAY 1 - APRIL 13th
Excavation began today on a custom built gunite swimming pool. The pool will have a kidney shaped spa with a small waterfall flowing into it. It will include a custom built gunite slide and larger moss rock waterfall. The pool also will have a 12" raised beam with two 3' sheer descents.