Creekside Park Custom Swimming Pool Construction Schedule - The Woodlands, TX

 

DAY 1 - March 2   EXCAVATION & STEEL

Beautiful weather to start construction on a swimming pool.  Despite the rain yesterday, we were able to find a dumpsite we could get into to dump the dirt excavated from the pool.  We left as much "good" dirt at the site as possible to help with the decking area around the pool.  The backyard has a slope to it.  Because of the slope, the deck and the pool in part of the yard are above the actual grade.  Spring Pools has to build up the grade to a level even with the back patio.  This keeps from having to install steps of the back patio.  The yard is narrow and we needed the space the steps would have required.

Spring Pools - Day 1 - Excavate   Spring Pools - Day 1 - Excavate

Spring Pools - Day 1 - Steel   Spring Pools - Day 1 - Steel

 

DAY 2 - March 3rd  GUNITE

Geometric pools require much more care in their construction.  Many calculations and measurements ensure the pool is square and symmetrical.  The sculpting of the gunite is more precise, thus much more "rebound" is produced.  Rebound is the extra gunite that is shaved off from what is blown on to the steel.  The final gunite shell is wonderfully crafted by Modern Method Gunite.

Spring Pools - Day 2 - Gunite   Spring Pools - Day 2 - Gunite

Spring Pools - Day 2 - Gunite   Spring Pools - Day 2 - Gunite

 

DAY 3 - March 4th  GUNITE CLEAN UP

Because there was so much gunite rebound produced in building the swimming pool, Spring Pools ordered the gunite clean up prior to any plumbing being started.

 

DAY 4 - March 5th  PLUMBING

The plumbing is started....

Spring Pools - Day 4 - Plumbing   Spring Pools - Day 4 - Plumbing

and finished in one day.  Spring Pools uses separated lines for each Sheer Descent to make sure there is plenty of water flow for each one of them.  The valves to regulate the water flow are placed at the pump, instead of running one line and placing valves at the Sheer Descents.

Spring Pools - Day 4 - Plumbing   Spring Pools - Day 4 -Plumbing

 

DAY 5 - March 6th  ELECTRICAL

The electrician for Spring Pools, J. Gomez Electric, is always flexible in his scheduling of work for us.  The Woodlands Township requires trench inspections, to ensure proper plumbing and electrical codes are followed.  The electrician is working on Saturday, so the trench inspection can be done on Monday.  A day it is suppose to rain.  Our subcontractors make the difference in having a swimming and spa built in less than one month, instead of more than two. 

Spring Pools - Day 5 - Electrical   Spring Pools - Day 5 - Electrical

DAY 6 - March 7th   SUNDAY

No work scheduled.

 

DAY 7 - March 8th   

No Work Scheduled due to Rain.  Trench Inspection approved.

 

DAY 8 - March 9th   TILE & COPING

The backer boards are set in place for the ceramic tile.

 Spring Pools - Day 8 - Tile & Coping  Spring Pools - Day 8 - Tile & Coping

 

DAY 9 - March 10th  TILE & COPING

The ceramic tile is set along with hand chipped flagstone coping.

Spring Pools - Day 9 - Tile & Coping   Spring Pools - Day 9 - Tile & Coping

Spring Pools - Day 9 - Tile & Coping   Spring Pools - Day 9 - Tile & Coping

 

DAY 10 - March 11th  TILE & COPING

The Tile and Coping is finished.  A beautiful finish to an elegant geometric swimming pool.

Spring Pools - Day 10 - Tile & Coping   Spring Pools - Day 10 - Tile & Coping

 

DAY 11 - March 12th  

No Work Scheduled.

 

DAY 12 & 13 - March 13th & 14th   SATURDAY & SUNDAY

No Work Scheduled.

 

DAY 14 - March 15th  DECKING

The form boards and rebar, for the concrete deck with pea gravel, are layed out and put in place.

Spring Pools - Day 14 - Decking   Spring Pools - Day 14 - Decking

 

DAY 15 - March 16th  DECKING

The deck is poured.

Spring Pools - Day 15 - Decking   Spring Pools - Day 15 - Decking

Spring Pools - Day 15 - Decking   Spring Pools - Day 15 - Decking

 

DAY 16 - March 17 

No Work Scheduled.

 

DAY 17 - March 18  INTERIOR FINISH

The swimming pool was cleaned and prepped for Pebble Sheen.

Spring Pools - Day 17 - Pebble Sheen   Spring Pools - Day 17 - Pebble Sheen

 

DAY 18 - March 19  INTERIOR FINISH

Desert Gold Pebble Sheen is applied to the interior surface of the pool.

Spring Pools - Day 18 - Pebble Sheen   Spring Pools - Day 18 - Pebble Sheen

 

DAY 19 -  March 20th  INTERIOR FINISH

The Pebble Sheen is buffed and acid washed.  The pool is filled the water.  

Spring Pools - DAY 19 - Pebble Sheen   Spring Pools - DAY 19 - Pebble Sheen 

 

DAY 20 - March 21st  SUNDAY

No Work Scheduled.

 

DAY 21 - March 22nd  FINSIHED

Pool equipment is started and a final clean up is done.  Pool School is set for next week.

 

30 Days Later....

 Square Spa, Sheer Descent, Fountains

Another Custom Built Ingound Gunite Swimming Pool Construction Project by the Contactors at Spring Pools.