Montgomery County Custom Swimming Pool Construction Schedule - Magnolia, TX

 

DAY 1 - March 11th   EXCAVATION & STEEL

Spring Pool begins the construction of a geometric swimming design.  The design includes a seven foot raised spa with a flagstone cascading spillway, a tanning ledge with two fountains, and a raised swimming pool beam.  The deck is designed to circle the pool and will step up to follow the raised pool beam. 

Spring Pools - Day 1 - Excavation   Spring Pools - Day 1 - Excavation

Spring Pools - Day 1 - Excavation   Spring Pools - Day 1 - Excavation

We also installed the stub plumbing for the pool on day one.

Spring Pools - Day 1 - Steel  Spring Pools - Day 1 - Stub Plumbing

 

DAY 2 - March 12th  GUNITE

Once again Modern Method Gunite does a superb job of guniting the swimming pool.

Spring Pools - Day 2 - Gunite   Spring Pools - Day 2 - Gunite

Spring Pools - Day 2 - Gunite   Spring Pools - Day 2 - Gunite

 

DAY 3 & 4 - March 13th & 14th  SATURDAY & SUNDAY

No Work Scheduled.

 

DAY 5 - March 15th  PLUMBING

Plumbing and equipment is installed

Spring Pools - Day 5 - Plumbing   Spring Pools - Day 5 - Plumbing

 

DAY 6 - March 16th  ELECTRICAL

Controls for the swimming pool are installed.

 

DAY 7 - March 17th   CLEAN UP

Clean up crew picks up trash; takes off form boards; and clears off the excess gunite.

DAY 8 - March 18th   TILE & COPING

Depending on the complexity of the pool, the tile and coping usually takes 2 to 3 days.

Spring Pools - Day 8 - Tile & Coping   Spring Pools - Day 8 - Tile & Coping

 

DAY 9 - March 19th  TILE & COPING

Tile and coping is completedfor this stage.  Once the deck is poured, the tile and coping materials will be used to finish out the step risers in the deck.

 

DAY 10 & 11  - March 20th & 21st  SATURDAY & SUNDAY

No work Scheduled

 

DAY 12 - March 22nd - DECKING

Laid out the forms, steel, and drains for the deck.

Spring Pools - DAY 12 - Deck   Spring Pools - DAY 12 - Deck

DAY 13 - March 23rd

No Work Scheduled

 

DAY 14 - March 24th  DECKING

Pour a pea gravel deck with a six inch step on both sides of the pool.

 

 

DAY 15 - March 25th  DECKING

Finished out the deck steps with the same materials used for the swimming pool coping and waterline tile.

 

 

DAY 16 - March 26th  PEBBLE TEC

The customer chose the Tahoe Blue Pebble Tec for their pool.  Today the pool is cleaned and prepped.

 

DAY 17 - March 27th   PEBBLE TEC

The Tahoe Blue Pebble Tec is applied to interior of the pool.

 

DAY 18 - March 28th  SUNDAY

No Work Scheduled

 

DAY 19 - March 29th  PEBBLE TEC

The Pebble Tec is given an acid wash and the pool begins to fill with water.