Alden Bridge Custom Swimming Pool Construction Schedule - The Woodlands, TXDAY 1 - July 13th EXCAVATIONStarted construction on an unique custom pool design. The pool was designed to incorporate an existing wood deck. Given the utility easement and the desire to have the spa positioned off the deck and a large entry for their daughter, the spa is going to be built within the pool entry. The first step will wrap around the spa, the second step will also be a large bench next to the spa.
DAY 2 - July 14th STEEL & STUB PLUMBING
DAY 3 - July 15th GUNITE
DAY 4 - July 16 PLUMBINGWhat a hot day. Temperature hovering near 100 degrees. The Spillers have been very kind in offering everbody plenty to drink. The Plumber and his crew were able to brave the heat and install all the plumbing, equipment and run the gas line in just over a day. Thanks everybody.
DAY 5 - July 17 ELECTRICALThe electrical system for the pool was installed. Trenches were inspected, then backfilled.
DAY 6 & 7 - July 18 & 19 WEEKENDNo Work Scheduled. Gunite being watered.....To keep from Cracking!
DAY 8 - July 20No Work Scheduled due to Rain.
DAY 9 - July 21 TILE, COPING & ROCKRock work along with tile and coping is started today. Depending on the size and complexity, the work can take several days. The Spillers chose to have flagstone waterline tile and flagstone coping. The pool also has a mini waterfall and seven weepers. The weeping rock is set into the beam of the pool wall to a point below the waterline. This design gives the pool a barrier from the yard, keeping unwanted debris out of the pool. This design also allows the pool to be placed next to the utililiy easements, allowing for a larger pool in a smaller backyard. The deck area is maximized between the house and the swimming pool.
DAY 10 - July 22 TILE, COPING & ROCKFininshed setting the moss rock for the Waterfall and Weeping Rock. Also, the Tile and Coping was fininshed being installed. What a beautiful water feature on a free form pool. The flagstone tile and coping accents the moss rock very well.
DAY 11 - July 23rd DECKThe deck for the pool is started. The deck is laid out. The drains are installed. The steel is set into place.
DAY 12 - July 24 DECKThe pea gravel deck is poured, floated, and finished. We added an umbrella sleeve in the deck so the Spillers could shade themselves by the pool. The deck was poured level to the existing wood deck for an easy transition.
DAY 13 - July 25 PEBBLE SHEENThe pool is prepped for Pebble Sheen. The Spillers decided on Blue Granite Pebble Sheen. Pebble Sheen has a smaller aggregate than Pebble Tec, but the application process is the same.
DAY 14 - July 26 SUNDAYNo Work Scheduled.
DAY 15 - July 27 PEBBLE SHEENThe Pebble Sheen is installed in the pool. It has a milky coating that will be acided washed.
DAY 16 - July 28 PEBBLE SHEENThe Pebble Sheen is acid washed. The pool return fittings are installed. The pool is then filled with water.
Three Weeks Later....Another Custom Built Inground Gunite Swimming Pool Construction Project Completed by the Contractors at Spring Pools.
|